Power & Heat

Modernization of the Schwerin South CHP Plant

Details
Auftraggeber
Energieversorgung Schwerin GmbH & Co. Erzeugung KG
Land
Germany
Standort
Schwerin
Zeitraum
02/2019-07/2022

Modernization of the Schwerin South CHP Plant

Our services:

  • Construction of switchgear building with central control room and 50 MVA transformer
  • Replacement of the existing transformer (capacity upgrade)
  • Reconstruction of the transformer station including wastewater system (oil and fire water containment)
  • 0.4 kV switchgear: modernization of the 0.4 kV systems of AHK1 and AHK2
  • Separation of the 0.4 kV systems in AHK1 and AHK2 as well as shared facility components
  • Integration of shared 0.4 kV system into the Block 3 switch
Themen

Weitere Referenzen